To facilitate for a major Next Generation 300mm Manufacturing Equipment Installation project for a Confidential Client in Ireland, DPS were engaged to manage and execute the entire Equipment De-installation Program.
Location:Ireland
Sector:Advanced Technology Facilities
About This Project
To facilitate for a major Next Generation 300mm Manufacturing Equipment Installation project for a Confidential Client in Ireland, DPS were engaged to manage and execute the entire Equipment De-installation Program. Direct responsibilities included: full design of the local specific equipment de-installation packages; procurement of all contracts; management of the equipment decommissioning and decontamination process; equipment safety sign-off; de-installation; move-out/ logistics; and asset management – as per our Client’s requirements.
Process / Support Systems
De-installation of 200mm and 300mm manufacturing equipment to enable next generation 300mm Client ramp capacity.